GE and Eneva:
PARTNERS IN POWERING
BRAZIL'S PROGRESS
GE and Eneva collaborated to keep the Parnaíba thermal power plant viable during a drought. Despite roadblocks, the long-time partners completed power plant outage services—a two-phase, two-outage project to maintain uninterrupted power to the grid—in record time.
Leading the way to decarbonization
Contents
Hydropower generates 80% of Brazil’s power.
But in a drought, production drops— so thermal power must compensate.
Their two 7F gas turbines were 4,000 hours over their 32,000 hour operational limit.
GE and Eneva needed to work fast to advance the outage start by 30+ days.
Having the right people, in the right place, at the right time was critical.
Building the right team was the first step.
Materials had to be onsite quickly.